City of Baker Springs, Tennessee

Resolution R-54-2023

COUNCIL DISTRICT(S) AFFECTED: Fourth (4)

BACKGROUND: A commercial building renovation is proposed at 300 Abraham Avenue. The proposed Easement Agreement includes the following:

  • Abraham Avenue –
    • Existing façade elements
    • Proposed metal coping on existing parapet to protrude 8 inches.
    • Proposed brick rowlock sill to protrude 3.5 inches at an approximate height of 19 feet 3 inches above the sidewalk.
    • Proposed 8 gooseneck wall sconces to protrude 2 feet 8 inches at an approximate height of 15 feet 3 inches at the highest point and 13 feet 4 inches at the lowest.
    • Proposed 1 inch x 6 inch cementitious trim and paneling to protrude 1.5 inches at an approximate maximum height of 13 feet and an approximate minimum height of 10 feet 2 inches.
    • Proposed 4 stucco piers to protrude 3.25 inches

OPTIONS: Approve or deny the recording agreement.

RECOMMENDATION: Approve the agreement.

ESTIMATED PROJECT SCHEDULE: Upon execution of the proposed Easement Agreement, project building permits can be finalized.

PRIOR ACTION/REVIEW: None

FISCAL INFORMATION: None